Completed ahead of schedule

Pathway Paving Project at Hey Joe Brewery, Franschhoek

Franschhoek, Western Cape

Completed: 13 December 2024

Comprehensive pathway paving installation at Hey Joe Brewery’s newly built hotel using exposed aggregate interlocking pavers and concrete block pavers, completed 2 days ahead of the critical opening deadline.

Project Summary

This case study covers a large-scale pathway paving project at Hey Joe Brewery’s new hotel in Franschhoek. Despite scheduling challenges with multiple contractors on site, the project was completed two days ahead of schedule using expert planning, extended working hours, and high-quality exposed aggregate and concrete block paving in full compliance with SANS paving standards.

Project Overview

The Hey Joe Brewery project in Franschhoek required professional paving contractors to install a high-quality pathway paving system for a newly built hotel ahead of its opening. The client’s goal was to complete the paving by 15 December 2024 to ensure the hotel was ready for guests by 17 December 2024.

Project Details

Location

Hey Joe Brewery, Franschhoek, Western Cape

Project Type

Commercial Hospitality Paving

Scope of Work

Install a comprehensive pathway paving system on newly constructed hotel property, including main walkways, guest access routes, and interconnecting sections

pathway paving installation

Client Goals & Requirements

Critical Timeline

Complete all paving installation by 15 December 2024 to ensure hotel opening on 17 December 2024, ready for guest arrivals during the peak holiday season

Key Project Features

Exposed Aggregate Pavers

Interlocking System

Concrete Block Pavers

SANS 1200 Compliance

Hospitality Grade Durability

Weather Resistant Finish

pathway paving installation

Project Challenges

Complex coordination requirements and tight scheduling constraints presented unique challenges for our experienced paving contractors in Cape Town.

Multiple Contractor Coordination

An extensive contractor presence on site required careful coordination and sequencing of work phases. Our paving team had to wait for other trades to complete their sections before beginning installation.

Impact: Potential delays and workflow disruption affecting the critical timeline

Work Demolition & Rework

Completed paving sections occasionally needed to be removed to allow other contractors access to underground utilities, requiring reinstallation after their work was completed.

Impact: Extended labour hours

Scheduling Complexity

Proper scheduling proved to be a major challenge with multiple interconnecting sections requiring precise timing coordination across different trades and phases.

Impact: Risk of missing the critical hotel opening deadline

Interconnecting Sections

Multiple pathway sections needed to integrate seamlessly while accommodating ongoing construction activities in adjacent areas of the hotel property.

Impact: Quality control challenges and potential installation inconsistencies

Solutions Implemented

Our experienced team overcame every challenge through proven techniques, extended work hours, and adherence to South African paving standards.

Extended Work Hours

Implemented an extended daily work schedule from 8:00 AM to 10:00 PM to maximise productivity and maintain the project timeline despite coordination challenges.

Result: Maintained critical deadline while accommodating other contractor schedules

Flexible Installation Approach

Developed adaptive installation methodology allowing for temporary removal and professional reinstallation of paving sections when required by other trades.

Result: Zero quality compromise while enabling seamless multi-trade coordination

SANS 1200 Standards Compliance

Maintained strict adherence to South African paving standards (SANS 1200MJ) throughout all phases, including rework sections, ensuring consistent quality and durability.

Result: Professional-grade installation meeting all regulatory requirements

Advanced Project Coordination

Implemented detailed scheduling coordination with site management and all trades, creating flexible work sequences that accommodated interconnecting section requirements.

Result: Seamless integration of all pathway sections with perfect alignment

Technical Specifications

We used professional-grade materials and installation techniques, ensuring long-term durability and performance for high-traffic hospitality environments.

Paver Materials

Primary Type Exposed Aggregate

System Interlocking

Secondary Type Concrete Block

Surface Finish. Textured Non-Slip

Installation Details

Joint Type Sand Filled

Bond Pattern
Running Bond

Base Preparation
Compacted Aggregate

Edge Restraint
Concrete Haunching

Compliance Standards

SANS 1200 MJ Compliance

Commercial Grade Installation

Hospitality Traffic Rating

Weather Resistance

Performance Benefits

  • Superior slip resistance for guest safety
  • Excellent drainage characteristics
  • High traffic durability for commercial use
  • UV-resistant finish prevents fading
  • Easy maintenance and cleaning
  • Frost-resistant for the Western Cape climate
  • The interlocking system allows for expansion
  • Professional appearance maintains property value

Project Timeline

Efficient project execution with milestone tracking and early completion despite complex multi-contractor coordination requirements.

Request A Free Quote

Get Your Free Paving Quote Today

Ready to upgrade your driveway, pathway, or outdoor space? Book a free, no-obligation paving quote and see exactly what your project will cost, with no hidden surprises.

100% Free & No Obligation

Transparent Pricing (excavation, drainage & rubble removal included)

Fast Quotes Within 48 Hours

Reliable Team, We Show Up On Time

Anytime call us

+27 81 306 7709

Get Your Free Paving Quote