Completed ahead of schedule
Pathway Paving Project at Hey Joe Brewery, Franschhoek
Franschhoek, Western Cape
Completed: 13 December 2024
Comprehensive pathway paving installation at Hey Joe Brewery’s newly built hotel using exposed aggregate interlocking pavers and concrete block pavers, completed 2 days ahead of the critical opening deadline.
Project Summary
This case study covers a large-scale pathway paving project at Hey Joe Brewery’s new hotel in Franschhoek. Despite scheduling challenges with multiple contractors on site, the project was completed two days ahead of schedule using expert planning, extended working hours, and high-quality exposed aggregate and concrete block paving in full compliance with SANS paving standards.
Project Overview
The Hey Joe Brewery project in Franschhoek required professional paving contractors to install a high-quality pathway paving system for a newly built hotel ahead of its opening. The client’s goal was to complete the paving by 15 December 2024 to ensure the hotel was ready for guests by 17 December 2024.
Project Details
Location
Hey Joe Brewery, Franschhoek, Western Cape
Project Type
Commercial Hospitality Paving
Scope of Work
Install a comprehensive pathway paving system on newly constructed hotel property, including main walkways, guest access routes, and interconnecting sections
Client Goals & Requirements
Critical Timeline
Complete all paving installation by 15 December 2024 to ensure hotel opening on 17 December 2024, ready for guest arrivals during the peak holiday season
Key Project Features
Exposed Aggregate Pavers
Interlocking System
Concrete Block Pavers
SANS 1200 Compliance
Hospitality Grade Durability
Weather Resistant Finish
Project Challenges
Complex coordination requirements and tight scheduling constraints presented unique challenges for our experienced paving contractors in Cape Town.
Multiple Contractor Coordination
An extensive contractor presence on site required careful coordination and sequencing of work phases. Our paving team had to wait for other trades to complete their sections before beginning installation.
Impact: Potential delays and workflow disruption affecting the critical timeline
Work Demolition & Rework
Completed paving sections occasionally needed to be removed to allow other contractors access to underground utilities, requiring reinstallation after their work was completed.
Impact: Extended labour hours
Scheduling Complexity
Proper scheduling proved to be a major challenge with multiple interconnecting sections requiring precise timing coordination across different trades and phases.
Impact: Risk of missing the critical hotel opening deadline
Interconnecting Sections
Multiple pathway sections needed to integrate seamlessly while accommodating ongoing construction activities in adjacent areas of the hotel property.
Impact: Quality control challenges and potential installation inconsistencies
Solutions Implemented
Our experienced team overcame every challenge through proven techniques, extended work hours, and adherence to South African paving standards.
Extended Work Hours
Implemented an extended daily work schedule from 8:00 AM to 10:00 PM to maximise productivity and maintain the project timeline despite coordination challenges.
Result: Maintained critical deadline while accommodating other contractor schedules
Flexible Installation Approach
Developed adaptive installation methodology allowing for temporary removal and professional reinstallation of paving sections when required by other trades.
Result: Zero quality compromise while enabling seamless multi-trade coordination
SANS 1200 Standards Compliance
Maintained strict adherence to South African paving standards (SANS 1200MJ) throughout all phases, including rework sections, ensuring consistent quality and durability.
Result: Professional-grade installation meeting all regulatory requirements
Advanced Project Coordination
Implemented detailed scheduling coordination with site management and all trades, creating flexible work sequences that accommodated interconnecting section requirements.
Result: Seamless integration of all pathway sections with perfect alignment
Technical Specifications
We used professional-grade materials and installation techniques, ensuring long-term durability and performance for high-traffic hospitality environments.
Paver Materials
Primary Type Exposed Aggregate
System Interlocking
Secondary Type Concrete Block
Surface Finish. Textured Non-Slip
Installation Details
Joint Type Sand Filled
Bond Pattern
Running Bond
Base Preparation
Compacted Aggregate
Edge Restraint
Concrete Haunching
Compliance Standards
SANS 1200 MJ Compliance
Commercial Grade Installation
Hospitality Traffic Rating
Weather Resistance
Performance Benefits
- Superior slip resistance for guest safety
- Excellent drainage characteristics
- High traffic durability for commercial use
- UV-resistant finish prevents fading
- Easy maintenance and cleaning
- Frost-resistant for the Western Cape climate
- The interlocking system allows for expansion
- Professional appearance maintains property value
Project Timeline
Efficient project execution with milestone tracking and early completion despite complex multi-contractor coordination requirements.